High-level project plan

From EGADSSWiki

Jump to: navigation, search
         </tr>



</table>
Task Name Start Date End Date Duration
Inception Phase 29/09/2004
28/02/2005 107.79 days?
Elaboration Phase Paperchild (Component-level Design) 01/03/2005 15/04/2005 34 days?
Construction Phase 1: Strawman (Class-level Design) 07/10/2004 30/06/2005 189 days?
Construction Phase 2: Woodwoman 07/10/2004 30/09/2005 255 days?
----Refine specification 01/07/2005 28/07/2005 20 days
----Deliver funtional implementation 07/10/2004 01/11/2004 20 days
----End of Construction Phase 2 30/09/2005 30/09/2005 1 day?
Construction Phase 3: Ironcat 03/10/2005 31/12/2005 65.14 days
----Integrate EGADSS with TAPAS 03/10/2005 14/10/2005 10 days
----Deliver refined implementation 17/10/2005 28/10/2005 10 days
----Update technical documentation 31/10/2005 11/11/2005 10 days
--------QSet 31/10/2005 11/11/2005 10 days
--------User Documentation 31/10/2005 11/11/2005 10 days
Deployment / Transitioning: Diamondog 31/12/2005 31/03/2006 66 days
----Develop User Documentation 31/12/2005 26/01/2006 20 days
----Develop user education information 31/12/2005 26/01/2006 20 days
------Develop guided tour 31/12/2005 26/01/2006 20 days
----Deliver EGADSS & TAPAS|e-MS installation and deployment packagetd 06/03/2006 31/03/2006 20 days
----End of Transition Phase 31/03/2006 31/03/2006 0 days
Project ends 31/03/2006td> 31/03/2006 0 days